Former Georgia Pacific Paper and Pulp Mill

Size: Approximately 200,000 sq ft Biomass powerplant.


Scope: Permitting, engineering, asset recovery, asbestos abatement and complete demo. MIWEC acquired the scrap/demolition rights and performed all necessary pre- demolition permitting to be able to take down to slab entire building after removing asbestos and valuable equipment for resale.